Lithgow Raw Water Transfer Pipeline

Abergeldie Complex Infrastructure

Client:
Value:
Completion:

$5.5m

2019

Location:

Lithgow, NSW

  • 14.8km complex pipeline 

  • Steep gradients (up to 38%)

  • 4-10m working corridors 

  • Butt fusion poly welding

  • Hydrotesting 

  • Major rock trenching

Major contract for a Water Transfer Scheme from Springvale CoalMine to a new Water Treatment Facility at Mount Piper PowerStation (MPPS), operated by Energy Australia.

Green Civil Con’s scope of works included the installation of 710mm diameter HDPE, PN25 pipeline and dual communications conduits.

Our team commissioned and tested all pipeline components such as air valves, hydrants and scour valves.